Rebuild Project Database

This option re-syncs the information on the pages with the project database.

Accessed from:

Ordinarily, changes made to a drawing page are recorded in the project database so that the software can perform cross referencing, keep track of device IDs and wire numbers, etc. However, if the information on the pages becomes out-of-sync with the project database (for example if someone edits the DWG files outside of Bentley Substation ), the user will need to update the project database with the new information.

The software will examine the information on each page in the project and update the project database. This is similar to the Update Page function except that it includes all pages in the project, not just one.